Pre-Establishment Approvals(CFE)

Application for Drawing Approval

  • The Proponent shall submit Application on-line through the TS – iPASS portal (https://ipass.telangana.gov.in)
  • The applications are then sent to Department for scrutiny.

Processing of the Application:

  • Scrutiny of the forms are carried out and if there is any query it will be visible on the dashboard.
  • Post query resolution, department will raise the amount for payment for design approval.
  • Once the payment is made, the applicant will receive the payment acknowledgement.
  • If any further query is raised by department it will be visible on the dashboard.
  • In case no query is raised or query is resolved department will issue an approval or Conditional approval and it will be available on the dashboard

Checklist of Documents to be submitted with the Application

  • Agreement letter between Contractor and Owner
  • Contractor License Copy
  • Supervisor permit copy of the electrical in charge of the company
  • Electrical single line diagram from point of commencement of supply to the end use of electrical energy
  • The structural layout showing plan and elevations with sectional and safe clearances

Timelines for receiving Drawing Approval after submission of Complete Application:

  • Electrical Drawing Approval – 14 days

Pre-Operational Approvals (CFO)

Application for Installation Certificate

  • The Proponent shall submit Application on-line through the Department of Electrical Inspectorate portal (http://ceigts.cgg.gov.in).
  • The applications are then sent to Department for scrutiny.

Processing of the Application:

  • Once the documents are uploaded, payment for the application has to be made, once the payment is made, the applicant will receive the acknowledgement for payment.
  • On receiving the payment, department will start the pre-scrutiny will be carried out for the documents submitted. Based on the pre-scrutiny the department can raise query which will be visible on the dashboard.
  • Once the query is resolved, inspection will be scheduled for the site.
  • After completion of inspection, Form of order will be uploaded on the applicant’s dashboard, the applicant has to respond to the defects, if any raised by the department. Once the defects has been resolved, the applicant has to submit the compliance report.
  • The department will review the compliance report and if required raise query, once the query is resolved the department will issue the Approval Certificate. The certificate will be available in the dashboard.

Checklist of Documents to be submitted with the Application:

  • Work Completion Report from Supplier
  • Work Commencement Report(WR-I)
  • Work Completion Cum Test Report(WR-II)
  • List of Load Particulars
  • Transformer and other HV/EHV equipment test certificate
  • Copy of electrical design approval

Timelines for receiving Installation certificate after submission of Complete Application:

  • Red : 21 days
  • Pre Scrutiny of Application submitted towards Electrical Installation Certificate within 3 working days from date of submission of Application.
  • Inspection of the Installation will be conducted by the officer within 7 working days from date of completion of pre scrutiny.
  • Form of Order will be issued within 48 hours of after inspection.
  • Electrical Installation Certificate will be issued within 7 working days after submission of satisfactory compliance Report.